What is the relationship between GREF and PMECH

asked 2024-11-19 11:39:58 -0500

Based on this PPSPY post "What is the base value for the generator GREF? " the GREF is represented as

 GREF = DROOP*PMECH

However, I sometimes encounter cases where this equation is not giving the expected answer compared to PSSE simulations. Is this GREF equation a general equation for all governor models? or is the equation different for different models?

edit retag flag offensive close merge delete

1 answer

Sort by ยป oldest newest most voted
1

answered 2024-11-19 14:48:03 -0500

perolofl gravatar image

The equation is for TGOV1 governors only!

edit flag offensive delete link more

Comments

Thanks perolofl. Is there a source or guide on how to approach other governors? I found some other PSSE governor models where the equation still holds, and some where it holds in GSTR simulation, but not in grid-connected. While other times, it does not apply at all

Mohamed_M gravatar imageMohamed_M ( 2024-11-19 16:07:44 -0500 )edit
1

You have to do the same as PSSE does at initialisation! Calculate backwards into the model starting with output signal PMECH. Signal speed is zero.

perolofl gravatar imageperolofl ( 2024-11-20 03:21:31 -0500 )edit

Your Answer

Please start posting anonymously - your entry will be published after you log in or create a new account.

Add Answer

[hide preview]

Question Tools

1 follower

Stats

Asked: 2024-11-19 11:39:58 -0500

Seen: 24 times

Last updated: yesterday