I have 2 generators. Pgen1=30MW,Qgen=49Mvar, Pmax=125,Pmin=0. MBASE=147 Pgen1 =98MW,Qgen=21Mvar,Pmax=125,Pmin=0. MBASE=147

I am using GENSAL for the generators.

Thank you for the reply.

I have 2 generators. Pgen1=30MW,Qgen=49Mvar, Pmax=125,Pmin=0. MBASE=147 Pgen1 Pgen2 =98MW,Qgen=21Mvar,Pmax=125,Pmin=0. MBASE=147

I am using GENSAL for the generators.