Hi everyone,
I am running a 4-bus 3-Generator system in PSSE. I had added the models WT4G2 + REECA1 (WT4E2 was giving issues). I tried running before the wind model (WT4G2+REECA1) in a small network and the dynamics were fine. When I try to run the model with the same parameters in my bigger network, despite successfully getting a PF with 0 mismatch, once I "initialize" for the dynamic simulation I get a warning message about "initial condition suspects" + "network not converged at TIME". The abovementioned system runs fine with only synchronous generators.
So far I tried the following: - I read online it could be from the Power flow method selected, but as I mentioned above, I made sure there were no mismatches. - I have also re-created my network, in case files were corrupted
Can anyone help me? Why I am I getting this issues? Has anyone experienced difficulties with these renewable generators?
Thanks for your help.
2 | No.2 Revision |
Hi everyone,
I am running a 4-bus 3-Generator system in PSSE. I had added the models WT4G2 + REECA1 (WT4E2 was giving issues). I tried running before the wind model (WT4G2+REECA1) in a small network and the dynamics were fine. When I try to run the model with the same parameters in my bigger network, despite successfully getting a PF with 0 mismatch, once I "initialize" for the dynamic simulation I get a warning message about "initial condition suspects" + "network not converged at TIME". The abovementioned system runs fine with only synchronous generators.
So far I tried the following: - I read online it could be from the Power flow method selected, but as I mentioned above, I made sure there were no mismatches. - I have also re-created my network, in case files were corrupted
Can anyone help me? Why I am I getting this issues? Has anyone experienced difficulties with these renewable generators?
Thanks for your help.