Reloading PSS/E slows down simulations?
asked 2018-04-16 02:27:21 -0500
Anonymous
Hello,
I have been running simulations where I do a parametric sweep to vary some parameters for each simulation to plot the effect of these variables. An issue I encounter is that later simulations run significantly slower than early simulations; the first set of simulations finish in ~3 hours, while the last set of simulations never manages to finish.
I run the same script to initialize PSS/E each time. Is this wrong? Do I need to close the previous PSS/E process or something similiar before starting a new one? I have checked the memory usage of my account on the server farm I am connected to, and it is stable at 150-250 MB. Processing power is also at 1-2% so I can't see any obvious changes here as time goes on.
What could be slowing down my simulations?
Thank you.