1 | initial version |
----------------------------- MACHINE INITIAL CONDITIONS ----------------------------- BUS# X-- NAME --X BASKV ID ETERM EFD POWER VARS P.F. ANGLE ID IQ 1 1 0.6900 1 1.0204 0.0000 100.01 0.00 1.0000 7.79 0.0000 0.9801 4 4 220.00 1 1.0200 1.0376 -99.05 13.56 -0.9908 -5.32 0.2223-0.9546
INITIAL CONDITIONS CHECK O.K.
That's what I got after initializing. Both SBASE and MBASE are 100MVA, you can see that POWER=IQETERM and VARS=IDETERM. Why is that? Don't we usually use d for Pe and q for Qe?
2 | No.2 Revision |
----------------------------- MACHINE INITIAL CONDITIONS ----------------------------- BUS# X-- NAME --X BASKV ID ETERM EFD POWER VARS P.F. ANGLE ID IQ 1 1 0.6900 1 1.0204 0.0000 100.01 0.00 1.0000 7.79 0.0000 0.9801 4 4 220.00 1 1.0200 1.0376 -99.05 13.56 -0.9908 -5.32 0.2223-0.9546
INITIAL CONDITIONS CHECK O.K.
That's what I got after initializing. Both SBASE and MBASE are 100MVA, you can see that POWER=IQETERM POWER=IQxETERM and VARS=IDETERM. VARS=IDxETERM. Why is that? Don't we usually use d for Pe and q for Qe?
3 | No.3 Revision |
----------
----------------------------- MACHINE INITIAL CONDITIONS -----------------------------
BUS# X-- NAME --X BASKV ID ETERM EFD POWER VARS P.F. ANGLE ID IQ
1 1 0.6900 1 1.0204 0.0000 100.01 0.00 1.0000 7.79 0.0000 0.9801
4 4 220.00 1 1.0200 1.0376 -99.05 13.56 -0.9908 -5.32 INITIAL CONDITIONS CHECK O.K.
That's what I got after initializing. Both SBASE and MBASE are 100MVA, you can see that POWER=IQxETERM and VARS=IDxETERM. Why is that? Don't we usually use d for Pe and q for Qe?