PSSE trip generator simulation

I am doing a big system simulation, and I am interest in the system frequency response while a generator is tripped. My problem is that once I diconnect the machine, the system is not converged. This is my system's gen/load distribution, and the total disconncet MW is 1271MW at area North.

Area  North  Middle  South

Load 15099.7 11600.7 12566.5 MW

Gen 10812.8 13498.9 14583.9 MW

I think it may be because the power generation in the north is too small, or the governor response is not enough to support the generation loss. Can anyone gives me a possible answer that I can solve this problem? Thanks.