Energy storage system active power output delay
Hello everyone: I knowed that the power output of energy storage system in PSS/E is according to the value set in fdbd, but is it also related to the time when the system inertia ends after N-G fault? Because during the simulation, I found that the energy storage system seems to start to output active power after the inertia response ends. Is this because of the limitations of the three models of REECA, REGCA, and REPCA? Or is there something wrong with my parameter setting?
Sincerely, thanks.