Monitorized line for droop compensation

asked 2021-09-23 04:39:18 -0500

pff gravatar image

If the system is the following: 999 SLACK BUS 10 POI 9 HVTRANSFORMERLEVEL 8 MVTRANSFORMERLEVEL There is a interconnection line between 9 and 10.

The PCC is regulating at 10 and the droop compensation is activated with Kc=0.05.

In REPCA model ICON: M=10 But which line should be monitorized? M+1=10 M+2=999 Or M+1=999 M+2=10