First time here? We are a friendly community of Power Systems Engineers. Check out the FAQ!

Ask Your Question
0

Possible to change load MW value during dynamic simulation

asked Nov 6 '18

bikiran1991 gravatar image

Hi,

I was wondering if its possible to change the load MW and MVAR while a dynamic simulation is running in PSSE. If possible, please let me know how.

1 answer

Sort by » oldest newest most voted
0

answered Nov 7 '18

jconto gravatar image

Check the post 'dynamic simulation with load change' or search for "load change".

link

Your Answer

Please start posting anonymously - your entry will be published after you log in or create a new account.
Want to format code in your answer? Here is a one minute demo on Youtube

Add Answer

[hide preview]

Question Tools

1 follower

Stats

Asked: Nov 6 '18

Seen: 178 times

Last updated: Nov 06 '18