Help regarding line fault contingency setup
I am trying to add a three-phase fault contingency in my system in between BusA and BusB. I am new at this and seeking for your help.
I am adding the commands in contingency file like below.
At Time 5 seconds Three Phase Fault on Line X ; BusA ; BusB; LineID 5% distance from from end /my fault clearing time is 5cycles, At time 5.1 seconds Clear Three phase fault on line at near end At Time 5.2 seconds Clear Three phase fault on line at Far end
But the program is not running with this code. Could you please tell me where is the issue?
Thanks a million for this.