What is your "extended term" simulation time?

PTI PSSE experts talking on this issue recommended to use the standard dynamic package by increasing the simulation time to the large values as needed for your 'extended term' simulation. The reason given was that the 'extended term' dynamic model were not keeping up-to-date as those in the standard package are.