Ask Your Question

Revision history [back]

click to hide/show revision 1
initial version

hi fluces, I have run contingency analysis(ACCC).At first ,I randomly selected the contingencies for PV analysis.After your suggestion I tried after ranking contingencies but still that didn't make much difference.(the ranking was done based on manually calculated Performance Index for power and voltage)

Is there direct tool in PSS/E 33 for contingency ranking?